Installation and commissioning of impact crusher

Installation and commissioning of the impact crusher :

Installation: Select the installation location according to the scope of the machine, and ensure that there is sufficient maintenance space.

debugging:

1. The rotor has been balanced before leaving the factory. Users generally do not need to perform balance test. When replacing the hammer and rotor parts, they should be balanced.

2. The main machine installation should be balanced, the spindle horizontality error is less than 1mm/m, the main driven wheel is in the same plane, the belt is adjusted to be tight and the motor is fixed.

3. Check that the mounting position of each component is moving, deforming, locking all bolts, and check that the seal is good.

4. Check the wiring and fastening of the electrical box, adjust the delay relay and overload protector, turn on the circuit, test the motor steering, and select the fuse of the appropriate specification.

5. Check the hydraulic system for reliable operation and leakage.

6. Remove the foreign matter in the impact crusher and move the rotor by hand to check for friction or collision.